“ … Here is another one. A change in what Human nature will allow for government. "Careful, Kryon, don't talk about politics. You'll get in trouble." I won't get in trouble. I'm going to tell you to watch for leadership that cares about you. "You mean politics is going to change?" It already has. It's beginning. Watch for it. You're going to see a total phase-out of old energy dictatorships eventually. The potential is that you're going to see that before 2013.

They're going to fall over, you know, because the energy of the population will not sustain an old energy leader ..."
"Update on Current Events" – Jul 23, 2011 (Kryon channelled by Lee Carroll) - (Subjects: The Humanization of God, Gaia, Shift of Human Consciousness, 2012, Benevolent Design, Financial Institutes (Recession, System to Change ...), Water Cycle (Heat up, Mini Ice Ace, Oceans, Fish, Earthquakes ..), Nuclear Power Revealed, Geothermal Power, Hydro Power, Drinking Water from Seawater, No need for Oil as Much, Middle East in Peace, Persia/Iran Uprising, Muhammad, Israel, DNA, Two Dictators to fall soon, Africa, China, (Old) Souls, Species to go, Whales to Humans, Global Unity,..... etc.)
(Subjects: Who/What is Kryon ?, Egypt Uprising, Iran/Persia Uprising, Peace in Middle East without Israel actively involved, Muhammad, "Conceptual" Youth Revolution, "Conceptual" Managed Business, Internet, Social Media, News Media, Google, Bankers, Global Unity,..... etc.)
.

Thursday, November 19, 2009

PLN to fine contractors delaying projects

Antara News, Thursday, November 19, 2009 17:24 WIB

Jakarta (ANTARA News) - State-owned electricity company PLN will fine contractors delaying the completion of their projects under the 10,000 megawatt (MW) power plant projects, a PLN director said.

PLN`s director for strategic construction affairs Agung Nugroho said here on Thursday that the fine would be imposed on contractors who could not show acceptable reasons of the delay.

"The fine has been stipulated in the contracts," he said.

He said that the fine amounts up to five percent of the total contract value, which comes to one per mill per day.

In the meantime, contractors could also lodge a complaint if PLN delayed payments.

PLN estimated that only about 915 MW of the projected 1,890 MW under the 10,000 MW mega project crash program would be completed at the end of this year.